A happy team (minus Carolyn who was off electrofishing) after the job was completed. We had a long week at Davington but were very pleased to walk off site on the Friday have achieved everything we set out to do.

All waste materials was removed from the site and went to be recycled as lowering the environmental footprint of this project wherever possible was a key consideration.

There was a lot of drilling ahead of the grout being poured. Having the right tools is key to being able to work efficiently in these situations.

A waiting game now! Once the chemical is poured into the holes it becomes a waiting game for the grout to start expanding and breaking the concrete apart.

Drilling into a piece of concrete removed from the burn – this acted as a control piece for us to be able to monitor the reaction of the grout in the concrete without any influence of water.

Pouring demolition grout into a drilled hole. Whilst the basic methodology for this technique is relatively simple there are tricks to getting the best outcome and whilst this project went well and worked, we learnt a lot from it and will tweak methods slightly going forwards.

Before – this weir had stood at this site for around 200 years and limited salmon and trout migration due to the shallow take off pool below the weir.

After – five days later and the burn was returned to a natural state where salmon and trout have unhindered access to the upper reaches of the Davington Burn.
Hi, is there any plans to use that grout method anywhere on river Irvine catchment?kind regards